Constructing Yanouh (Wadi Jilo) Pumping Stations to Provide Water to Some Villages in Tyre Caza
Scope of Work
The project works consist of:
- Public works including sidewalks construction, concrete and asphalt paving for public areas, external lighting, electric cabling and power group installation landscaping and garden plantation and irrigation works; storm and sewer line concrete and natural storm retaining walls, excavation demolition and fencing works.
- Structural and finishing works of the main building (management): including concrete and reinforced concrete works, masonry works, plastering, rendering and spatter dash, painting, tiling and natural stone cladding, roof tiles and attics, wood works steel and aluminium, kitchen and toilets supplements, electric works and internal lighting, sanitary fixtures and plumbing, and water proofing.
- Works also include the installation of submersible and auxiliary pumps with the pumping mains and related automation control system, chlorination units and the electric installation.
Notification Order & Commencement: No.7068 10/04/2002
Completion: 13/05/2004