Tyre Old City Urban Component Phase III (Chud): Rehabilitation Of Bawabeh Square And Parking

Country: Lebanon

Location within country: Tyre, South Lebanon

Client: Council for Development and Reconstruction (CDR)

Financed by: IBRD

Consultant: Rafik El Khoury & Partners

Scope of Work

The works mainly comprise interventions in Tyre Old City for Urban Improvement at Al Bawabeh Square Area which include but are not limited to:
I – BAWABA SQUARE

A- Civil Works:

  • Site Works: Demolition, excavations, fill, flexible pavement, sub- grade preparation, sub drainage, rehabilitation of the existing public sanitary sewer and potable water systems where needed, relocation of existing utilities, rigid pavement, stone paving and flooring, stone pavers, natural curbstone , public storm drainage, manhole grade adjustment.
  • Tiling Works: Tiling of Bawabeh Square with basalt, granite, agglomerate and cement tiles.
  • Cast-in- Place Concrete Works: Underground water tank, pump room, retaining walls, sidewalks beams, encasement for PVC pipes, toilets and stairs.
  • Masonry Works: Hollow concrete blocks for toilets.
  • Metal Works: metal fabrications (steel structure, aluminum frames, doors and windows).
  • Finishing works: stone paving and flooring, ceramic tiles, painting, high performance coatings, dimension stone tile, Portland cement plaster.
  • Specialties: Roofing and waterproofing, agricultural soil, planting and accessories, landscape.  
  • Furnishings: Wooden Kiosk, Benches and dustbins.

 

B- Mechanical Works

  • Sanitary Works: sanitary pipes and fittings, plumbing fixtures, municipal sewer connection, valves, mechanical insulation, drainage and vent systems.
  • Storm drainage Works: Domestic water pump and piping, drainage and vent piping, plumbing fixtures and potable water storage tanks.
  • HVAC Works: Metal ducts, power ventilators and grilles.

C-Electrical Works

  • Builder’s work, cables, pits, earthing systems, street lighting, luminaries, lighting outlets, and ducting; MV and LV networks, removal and relocation of existing networks.

 

II – PARKING PARCEL 1010
A- Civil Works:

  • Site Works: Demolition, excavations, fill, flexible pavement, sub- grade preparation, sub drainage, rehabilitation of the existing public sanitary sewer and potable water systems where needed, relocation of existing utilities, rigid pavement, stone paving and flooring, stone pavers, natural curbstone , public storm drainage, manhole grade adjustment.
  • Tiling Works: Tiling of Parking with turf-stone, interlock and cement tiles.
  • Cast-in- Place Concrete Works: Entrance and exit ramp, retaining walls, tie beam and stairs.
  • Furnishings: Gabion wall fences and dustbins.

B- Electrical Works

  • Builder’s work, cables, pits, earthing systems, luminaries, lighting outlets, and ducting; LV networks, removal and relocation of existing networks.

Notification Order: 08/10/2015